Yelm Projects and Programs Manager highlights projects in the works for 2027 and beyond

Posted

The City of Yelm’s Projects and Programs Manager, Brad Chatwood, provided an update on some of the city’s “big projects” in the works for 2027 and beyond during a Yelm Planning Commission meeting on Tuesday, Nov. 17.

First, Chatwood highlighted the long-awaited roundabouts at SR 507 and Bald Hill Road, and at Bald Hill Road and Morris Road. He noted the roundabouts are currently at 60% design, and that engineers are entering the final design stage of the project.

“There’s a lot of moving pieces in this work,” Chatwood said. “Tentatively, our schedule shows us going to construction in early 2028. The timeline has pushed a bit. We’re making progress. Slowly, but surely.”

Chatwood added that the roundabout at SR 507 and Bald Hill Road is fully funded by the state, and noted Washington State Department of Transportation (WSDOT) came to the City of Yelm “asking if they had interest in the project.”

Funding for the roundabout at Bald Hill Road and Morris Road, however, is still up in the air. Chatwood said the City of Yelm applied for a highway safety grant to go toward funding the project, however, it was unsuccessful in its grant application.

“We are leaning on our legislature to acquire those funds, as well as looking elsewhere,” Chatwood said. “These two roundabouts have to go together as a system, and WSDOT agrees with that. That’s why they’re allowing us to design them together, because they work together. Everyone knows this has to happen. It’s just a matter of finding the funds, and we’ll get there.”

Chatwood then highlighted the anticipated Rhoton Road reconstruction project, which has already drawn a lot of discussion from Yelm City Council. With the Yelm Loop soon going to construction and arriving for commuters to avoid inter-city traffic, the City of Yelm anticipates Rhoton Road becoming a major arterial into town from the new bypass.

“Reconstruction of Rhoton Road is on the docket,” Chatwood said. “We’ll have sidewalks on one side, a shared-use path on the other side connecting to the trail, landscaped, wider lanes and a new water main. There’s a lot happening on this one as well.”

Chatwood noted there will be rapid flashing beacons at a crosswalk for youth from the Donovan Court and Prairie Creek Loop to safely cross the road at.

He said these plans are currently at 60% design, and claimed the City of Yelm is currently working on right-of-way acquisition.
Chatwood anticipates a construction date of Jan. 2028 for this project.

Chatwood also highlighted the Fuller Footpath project, which the City of Yelm secured funding for with help of Congresswoman Marilyn Strickland’s office. He said the project is nearing completion of phase one, with utilities being moved underground.




“There’s been talk of the farmer’s market moving over there,” Chatwood said. “We’re going to be able to accommodate food trucks. It’s a gathering area for certain events and for business owners who want to have a barbecue or places to gather outdoors. I think it’s a big benefit.”

Next, Chatwood highlighted water main improvements set for Creek Street.

“We actually have our pre-construction meeting (on Wednesday, Nov. 18),” Chatwood said. “Construction will start on this in the next couple of weeks. So beware, when you’re driving around town, that you may want to avoid Creek Street for a little while.”

He added that traffic control will be present during construction on Creek Street.

Additionally, Chatwood said the City of Yelm wanted to get this project “done and out of the way” with the roundabouts set for construction in the next year and a half.

“The last thing we want to do is come in and construct a roundabout, tear it up and put in a new water main,” Chatwood said. “That will be coming soon. Hopefully, we’ll be done with that one in March-ish of next year.”

Chatwood added that from Algiers to 103rd Street, on the west side of the road, sidewalks will also be installed.

The next project to be highlighted was a sidewalk connection project at Railway Road and Middle Road.

“With the new Shell Meadows development that has come in, we felt this would be a good opportunity for us to make a connection with sidewalk to the other side of the road,” Chatwood said. “Some of those kids are probably walking to Fort Stevens for school.”

He added that designs for the project are 100% completed, and that the city is now working on acquiring right of way. Chatwood noted the property owner is willing to sell right of way access to the city.

Construction is expected to begin in spring of 2027 and conclude in the subsequent summer.