In a special city council meeting Tuesday, July 22, the City of Roy unanimously voted to approve a motion that allows Clerk-Treasurer Kris Ballerini to request that the Washington state Department of Transportation (WSDOT) reallocate funds for the city’s crosswalk project across state Route 507.
“For the crosswalk, we were informed by WSDOT that we do need to do a fund reallocation,” Mayor Kimber Ivy said during the meeting. “And just for recap for everybody on how this works, is the $200,000 grant that we received, we don't technically get the money in. We hold all of our receipts, and we put it in for reimbursement.”
Ivy added that the money has to be allocated before the project starts. She said $100,000 was earmarked for construction and set aside, and then the rest of the funds were put into planning.
“When planning was done, we then moved the funds to design,” Ivy said. “During all of that, a portion of the money, $11,694, was earmarked for ‘agency.’”
Ivy then asked Ballerini to speak on the matter. Ballerini said that the $11,694 was allocated for a “workforce agency,” and, because the city is not in that phase, WSDOT suggested submitting an application to move the $11,694 into the “consultant fees” category.
In this case, the money would, ostensibly, be used to pay Skillings, the engineering firm contracted for the project — or else other consultants tied to the project’s next phase.
“Because it's there for us to use, but right now, it's being earmarked as this agency that we aren't going to use at all,” Ballerini said.
In an email to the Nisqually Valley News, Mayor Ivy confirmed that the $200,000 grant falls under the 2023–25 State Transportation Budget and includes both the installation of the flashing pedestrian crossing sign across state Route 507 and the construction of a sidewalk along Huggins Greig Road.
“Although there was an initial internal breakdown of $100,000 for design and $100,000 for construction, WSDOT’s award letter specifies only a lump sum of $200,000 without a mandated internal split,” Ivy wrote. “That said, based on subsequent budgeting and state transportation updates, the construction portion of the project has now been moved to ‘future’ status — likely post-2030, pending supplemental budget adjustments or alternate funding.”
The city had hoped to start construction on the crosswalk project this past June. On June 9, Rep. Andrew Barkis, speaking to the Roy City Council, said the indefinite push was more of a “clerical error.”
During the July 22 meeting, Councilmember Yvonne Starks said the council has seen no drawings of the crosswalk, and asked if they were going to get something for the money that has already been spent. Ivy said that plans should be coming to the council once WSDOT approves them.